Sunday, June 8, 2014

Day 49: Ancillary Projects

Day: 49
Schedule: Running Over
Prognosis for Survival: Eh ...

There's a small problem with one of the leveling feet on the stove; we have a call in for service but that conspired with getting the subcontractors coordinated means it looks like our completion date is slipping by a few days to the middle of next week instead of the end of this one.

It's not part of the project, but as I noted back on Day 22, the retaining wall in the garden looks pretty bad and repainting it is probably inevitable. I borrowed a pressure washer from a neighbor and between that and a belt sander, cleaned it up a lot ... Evelin says it still needs to be painted, however. (Also, patchy as it is, there is some grass taking hold atop the mulch we put down after all the brush that existed along the old fence line.)